Progress report week 16

During this week the builders have been working hard in the loft, the door frame, last of the insulation and the walls have all gone up. We are now waiting for the stairs which may well be late next week. They have also started plastering up there.
Chris has also done some rearranging and plumbing in the bathroom.

For more photos see loft here, outside hereand bathroom here

Sunday, 28 June 2009

Down comes the old kitchen ceiling.

The ceiling had to come down so I can sort out more plumbing. I was only going to take down a bit of the ceiling but then half of it came down when I wasn't expecting it. I made more mess than I had planned.